As required by the City of Portland, the University will be completing required measures to take care of non-conforming issues in the main parking lot this summer. Workers will install 28 curbed planter areas with 54 new trees and an accessible crosswalk between the soccer field and Franz Hall. The plan is to start with the crosswalk and planters in the middle of the lot and then work towards the Pilot House. Lanes will be closed as needed to complete each section of this work and will create turn lanes to access all areas of the lot. Each closure will take 100 spaces off line and will take approximately two to three weeks to complete. There will be a website to track progress and to show lane and parking closures with routing changes.
If you have any questions or concerns, please contact Paul Luty at x8874 or luty@up.edu.